STC calculator: what your solar or battery discount is worth (2026 and 2027)
As at November 2026, rooftop solar earns kW × your postcode’s zone rating × 5 years of certificates if installed in 2026, and 4 years from 1 January 2027. A battery earns 6.8 per usable kWh, falling to 5.7. A 6.6 kW system in Melbourne gets 39 STCs, about $1,544 at $39.60; a 13.5 kWh battery 91, about $3,604.
Written by Juan Flinn, Content Editor · Reviewed by the Mission Green Energy Team · Updated 9 November 2026
What are your
certificates worth?
Change any input and the answer recalculates. Nothing you type leaves this page.
$39.60 is the price Mission Green credits per certificate on a quote, as at November 2026. Installers pass through a price of their own choosing, not the market price on the day, so put in the figure from your quote.
Rooftop solar
Home battery
Certificates are rounded down to whole numbers, as the regulations require, and dollars to the nearest dollar. Solar and a battery on the same job earn both amounts. Cross-check any result with the Clean Energy Regulator’s own STC calculator.
How do STCs
actually work?
One scheme, two formulas, and a date that does most of the work.
A small-scale technology certificate (STC) is created under the federal Small-scale Renewable Energy Scheme. For solar, the system is “deemed” to produce power for a set number of years, and all the certificates for those years are created up front. Because the scheme ends in 2030, the deeming period falls by one year every 1 January: 5 years for a 2026 install, 4 for 2027. Batteries earn certificates by usable capacity under the Cheaper Home Batteries Program, at a factor that steps down every six months. Most people assign the certificates to a registered agent in exchange for an upfront discount on the price, so you never sell one yourself.
| Zone | Zone rating | Example postcodes | 6.6 kW in 2026 |
|---|---|---|---|
| Zone 1 | 1.622 | Alice Springs 0870, Port Hedland 6721 | 53 STCs |
| Zone 2 | 1.536 | Darwin 0800, Broken Hill 2880 | 50 STCs |
| Zone 3 | 1.382 | Sydney 2000, Canberra 2600, Brisbane 4000, Adelaide 5000, Perth 6000, Ballarat 3350, Bendigo 3550 | 45 STCs |
| Zone 4 | 1.185 | Melbourne 3000, Geelong 3220, Hobart 7000 | 39 STCs |
The zone follows the postcode, not the city. Most of Melbourne is zone 4, but postcodes 3036 to 3038, 3047 to 3049 and 3061 to 3064 in the north and north-west are zone 3, so the same system there earns about 17% more certificates. The calculator above holds all 137 ranges of the official table.
What do common systems earn,
before and after 1 January?
Each row is the calculator above with those inputs, at $39.60 a certificate.
| System | How the count is worked out | Installed by 31 Dec 2026 | Installed from 1 Jan 2027 |
|---|---|---|---|
| 6.6 kW solar, Melbourne 3000 (zone 4) | 6.6 × 1.185 × 5 years, then 4 | 39 STCs · $1,544 | 31 STCs · $1,228 |
| 10 kW solar, Brisbane 4000 (zone 3) | 10 × 1.382 × 5 years, then 4 | 69 STCs · $2,732 | 55 STCs · $2,178 |
| 13.5 kWh battery (usable) | 13.5 × 6.8, then 5.7 | 91 STCs · $3,604 | 76 STCs · $3,010 |
| 27 kWh battery (usable) | (14 + 13 × 60%) = 21.8 × 6.8, then 5.7 | 148 STCs · $5,861 | 124 STCs · $4,910 |
The solar rows lose a fifth of their certificates on 1 January because the deeming period drops from five years to four. The battery rows lose about 16%, because the factor falls from 6.8 to 5.7. The 2027 battery figures hold until 30 June 2027; from 1 July the factor is 5.2, which takes the 13.5 kWh battery to 70 STCs ($2,772) and the 27 kWh battery to 113 ($4,475).
The 27 kWh battery earns less than twice the 13.5 kWh one because only its first 14 kWh count in full. Our guide to the battery tiers shows where each extra kWh stops paying, and the battery size calculator shows what each size actually saves on a Victorian bill. For the solar side, what size solar system you need matters more than the certificates.
What about solar
over 100 kW?
Since 1 October 2026, mid-scale solar earns STCs too, on a fixed five years.
Solar where the site total is over 100 kW and no more than 1 MW, installed on or after 1 October 2026, is mid-scale solar and can create STCs. Its deeming period is fixed at 5 years under the Mid-scale Solar amendment, so it does not fall on 1 January 2027. The count uses the same formula as household solar: kW × zone rating × 5, rounded down. A 200 kW system in Melbourne postcode 3000 comes to 1,185 STCs, about $46,926 at $39.60. The calculator above switches to this rule when you enter more than 100 kW.
The site total counts related solar on the same or adjoining sites, so a small addition can be mid-scale. The regulations’ own example is a 60 kW system added to a site with 30 kW of existing solar and a 700 kW accredited power station: 790 kW in total, so the 60 kW is mid-scale. Tick the site box in the calculator for that case. Above 1 MW, solar is a large-scale power station and earns LGCs, which our STC versus LGC guide compares.
Two cautions. The Clean Energy Regulator expects applications for mid-scale certificates to open in mid to late November 2026, and calls its own mid-scale STC calculator a guide only, so check your figure there. And mid-scale jobs need extra evidence that planning and approval requirements were met. Our guide to the 1 MW expansion covers what to put in the contract.
Why might your quote
show a different number?
Four reasons, and a quote that shows its working answers all of them.
1. The certificate price. The count is set by law; the price is not. The Clean Energy Regulator’s clearing house price is fixed at $40 excluding GST, but there is no guarantee how long certificates take to sell there, and the open market price changes daily. Your installer passes through a price of its own choosing. Ask for the certificate count and the price per certificate as separate lines.
2. Rounding and the inputs. Certificates are whole numbers, always rounded down. Solar is counted on the rated kW of the panels. A battery is counted on its usable capacity as listed on the approved battery list, not the bigger nominal figure on the brochure, and only the first 50 kWh usable count.
3. The date. Solar takes the deeming period for the year it is first able to produce and deliver electricity. For a battery, the regulations set the factor by the date the battery is certified as compliant with electrical safety laws, which is normally the day it is installed. A contract signed in December for a January install earns the 2027 count.
4. Eligibility. The panels, inverter and battery must be on the Clean Energy Council’s approved lists, new, and designed and installed by a Solar Accreditation Australia accredited designer and installer; a battery installer also needs the battery endorsement. A battery must be 5 to 100 kWh nominal capacity and able to join a virtual power plant, and only one battery claim is allowed per premises. The CER points buyers to the New Energy Tech Consumer Code’s approved sellers to find a retailer. You can check an installer’s accreditation in a minute.
STCs:
your questions, answered.
It depends on your postcode zone and install year. In Melbourne postcode 3000 (zone 4, rating 1.185) a 6.6 kW system installed in 2026 earns 39 STCs, about $1,544 at $39.60, and 31 STCs, about $1,228, if installed from 1 January 2027. In Sydney, Brisbane, Adelaide or Perth (zone 3, rating 1.382) it earns 45 in 2026 and 36 in 2027.
Multiply the system’s rated kW by your postcode’s zone rating and by the deeming period, then round down to a whole number. The deeming period is 5 years for systems installed in 2026 and 4 years for 2027, falling by one each 1 January until the scheme ends in 2030. Zone ratings run from 1.622 in zone 1 to 1.185 in zone 4, as published by the Clean Energy Regulator.
Usable capacity times the STC factor, tiered: the first 14 kWh count in full, 14 to 28 kWh at 60% and 28 to 50 kWh at 15%, with the total rounded down. The factor is 6.8 to 31 December 2026, 5.7 from 1 January 2027 and 5.2 from 1 July 2027. A 13.5 kWh battery earns 91 STCs now and 76 from January; a 27 kWh battery 148 and 124.
There is no single price. The Clean Energy Regulator’s clearing house price is fixed at $40 excluding GST, but there is no guarantee how long certificates take to sell there, and the open market price changes daily. Your installer passes through a price of its own choosing. Mission Green credits $39.60 a certificate on its quotes as at November 2026, which is this calculator’s default.
Yes, for both. Small-scale solar installed from 1 January 2027 is deemed for 4 years instead of 5, so it earns about a fifth fewer certificates: a 10 kW system in Brisbane drops from 69 to 55 STCs. The battery factor falls from 6.8 to 5.7 per usable kWh. Mid-scale solar, where the site total is over 100 kW, keeps a fixed 5-year deeming period.
Yes, since 1 October 2026, if the site total is over 100 kW and no more than 1 MW. These mid-scale systems have a fixed 5-year deeming period, so on the regulations’ formula a 200 kW system in Melbourne postcode 3000 earns 1,185 STCs, about $46,926 at $39.60. The Clean Energy Regulator expects applications to open in mid to late November 2026. Above 1 MW, solar earns LGCs instead.
The Clean Energy Regulator splits Australia into four zones by postcode. Melbourne 3000, Geelong 3220 and Hobart 7000 are zone 4 (rating 1.185); Sydney 2000, Canberra 2600, Brisbane 4000, Adelaide 5000, Perth 6000, Ballarat 3350 and Bendigo 3550 are zone 3 (1.382); Darwin 0800 and Broken Hill 2880 are zone 2 (1.536); Alice Springs 0870 and Port Hedland 6721 are zone 1 (1.622). Some northern Melbourne postcodes are zone 3.
Where these
figures come from.
Rules from the Clean Energy Regulator and the Renewable Energy (Electricity) Regulations 2001 as in force from 1 October 2026, read 10 November 2026. The postcode table is the CER’s “Postcode zone ratings and zones for solar (photovoltaic) systems”, as of 1 January 2020. This is general information, not financial advice.
- Clean Energy Regulator — Calculate STC entitlements: deeming periods, mid-scale 5-year deeming, battery factors
- Clean Energy Regulator — Postcode zone ratings and zones for solar (photovoltaic) systems, as of 1 January 2020 (Table 1)
- Clean Energy Regulator — Solar batteries: eligibility, STC factor and tiers
- Clean Energy Regulator — Small-scale renewable energy systems: eligibility
- Clean Energy Regulator — Mid-scale solar (100 kW to 1 MW)
- Clean Energy Regulator — Mid-scale solar STC calculator
- Clean Energy Regulator — Buy and sell STCs: clearing house price
- Federal Register of Legislation — Renewable Energy (Electricity) Regulations 2001, regulations 19D and 20 (compilation in force from 1 October 2026)
- Federal Register of Legislation — Renewable Energy (Electricity) Amendment (Mid-scale Solar) Regulations 2026